What is a hydrostatic test on a fire hydrant system?
Short answer
A hydrostatic test raises the whole fire hydrant system to 1.5 times its working pressure to prove the pipework, joints and valves hold without leaking. AS 1851-2012 requires it every five years where a fire brigade booster is fitted, before the booster flow test.
What changes the answer
Whether the system has a fire brigade booster (AS 1851-2012, Table 4.4.4, item 4.3); the system's working pressure under the standard it was designed to, usually AS 2419.1, so the test pressure differs from building to building; the order of work, as hydrant valves get new seatings before the test (item 4.7) and the booster connection flow test follows a pass (item 4.2); and the condition of the pipework, fittings and valve seats, as any leak is recorded as a defect, repaired and the test repeated.
What PMP does
- Works out the test pressure from the system's design pressure and the standard it was built to.
- Replaces hydrant valve seatings before the test, as AS 1851 requires.
- Tells building management before the system is taken out of service, and puts it back in service when the work is done.
- Records the result, and any leaks or defects, in the service report and the logbook.
- After a pass, carries out the booster connection flow test, using PMP's own fire truck where the system calls for a boosted test.
General information only. What your building needs depends on its systems, its approved design and its condition.