Hydrants & hose reels

In short

4 plain answers about hydrants & hose reels, written for building managers and fire companies, each dated and reviewed by PMP's compliance manager.

Updated

  • What is a water supply proving test?

    A yearly test that proves the water supply can deliver the flow and pressure the system was designed for, measured at the hydrant that's hardest to reach. It's required every year for hydrant systems under AS 1851-2012.

  • How often are hose reels serviced?

    Every six months and every year under AS 1851-2012. The yearly service includes opening the reel fully and checking the flow.

  • What is a hydrostatic test on a fire hydrant system?

    A hydrostatic test raises the whole fire hydrant system to 1.5 times its working pressure to prove the pipework, joints and valves hold without leaking. AS 1851-2012 requires it every five years where a fire brigade booster is fitted, before the booster flow test.

  • What is a hydrant block plan?

    A block plan is a diagram of the building's hydrant system, mounted at the booster or fire control point. It shows firefighters where the hydrants, valves and pipework are, so they can use the system quickly in a fire.